“Gym” dandy progress

Multimedia


Photos: Gallery | Slideshow

The maple flooring for the Athletic Performance Center and the Men’s Practice Facility have been delivered and installation of the subflooring will begin the week of January 18. Painting in the gym is complete and the retractable basketball goals have been installed.

Painting also continues in the APC. Ceramic flooring, carpet and wall tile are being installed in the the lower level and installation of sports flooring is scheduled to begin January 18 in the training room. Ceiling grids and lights also are being installed in these areas. And, passers-by on Main Street will notice that glass installation is continuing at the Lobby entrance area on the north end of the building.