Progress continues
The last roof truss has been installed on the Athletic Performance Center and the iron workers are now working on the north end-wall structural framing. The roofer has started installation work at the lower roof along the west side of the building and window installation is in progress. And, much work continues on the interior of the building.
Observers soon will see the large crane used to set the structural steel at the north end of the building at the southwest corner of the building for the installation of the precast wall panels on the Practice Gym.