In good form
Work continues on the second floor formwork of the Arena as reinforcing and electrical conduit are placed in sections already constructed. Plumbing, ductwork and electrical conduit are being installed in the west section of the basement above the ceiling.
Meanwhile, contractors are forming and pouring the walls that surround the south and west edges of the Arena floor area. They also are pouring structural walls in the south end of the building.
The second half of the basement floor area, the new chiller plant, will be poured the week of April 13 as will more footings for the walls along the east edge of the Arena floor.
The steam and condensate piping installation across Glenwood Avenue near Jobst Hall is progressing with the first two sections in place. Excavation and more pipe installation continues.