Concrete poured for first floor of new arena

About 600 cubic yards of concrete was poured for the first floor of the Athletic Performance Center on February 10.

Multimedia


Photos: Gallery | Slideshow

Preparation work for the first delivery began at 5 a.m. The first truck was in position at 7 a.m., and the crew pouring the concrete delivered the last load about 4 p.m. The finishing crew completed work on the new deck slab at about 9:30 p.m. A total of 85 concrete trucks delivered 595 cubic yards of concrete to the site that day.

By the numbers -

  • • Eleven men poured the concrete as it was pumped.
  • • Two pump truck operators pumped the concrete.
  • • Two technicians tested the concrete as it was delivered.
  • • One ironworker observed the pour to monitor reinforcement positioning.
  • • Two men below the formwork continuously checked the formwork elevation as it was filled with concrete.
  • • One man installed embed attachment plates for the pre-cast wall panels.
  • • One skid steer operator kept the ruts and mud cleared for the concrete trucks.
  • • One crane operator lifted the truss screed over the column locations
  • • Eight men and one woman finished the concrete.
  • • One plumber monitored floor drain positioning.
  • • One electrician monitored conduit positioning.